Full Bath Remodel Guide: Plan, Cost and Build in Melbourne

You're staring at two quotes that don't describe the same bathroom. One keeps the shower where it is. The other moves the waste, adds a tiled hob and a new fan, and the totals sit thousands apart. The vanity still looks fine, yet the silicone at the shower has gone black and the laundry ceiling below has a faint stain. A full bath remodel is the job that decides whether that stain is a fixture swap or a rebuild of everything behind the tile.

The visible work is the part neighbours notice. The work that sets the price, the weeks and the risk is the work you never see once the tiles go on. Read each stage at the moment a fault is still cheap to fix.

Full Bath Remodel Stages and Realistic Timelines

In a 1960s Brighton bungalow, a vanity can still work while a shower base leaks into the laundry ceiling below. A refresh may hide the symptoms, but a full remodel exposes the wet-area structure and checks it before new finishes cover the work. The visible stages can be quick. Repairs, curing and sign-offs set the schedule.

StageWhat gets doneTypical durationHold point before moving on
Design and quotesLayout, fixture selection, line-item quotes2-4 weeks, off siteSigned scope and fixed line items
Permits and approvalsBuilding surveyor or council confirms the pathway1-3 weeks before strip-outWritten confirmation of the permit pathway
Demolition and strip-outRemove tiles, vanity, old linings and waste2-4 working daysExposed substrate photographed and moisture checked
Rough-in plumbing and electricalNew waste, supply lines, wiring, fan duct3-5 working daysPlumbing rough-in sign-off recorded
Substrate repair and fallsFraming repair, sheeting, floor falls to waste3-5 working daysSubstrate smooth, clean, dry and sound
Waterproofing and curingMembrane at walls, floor, junctions and penetrationsPer membrane data sheetMembrane photos and product records kept
InspectionCheck coverage before concealment1-2 working daysInspection evidence recorded before tiling
Tiling, grouting and sealingWall and floor tiles, grout, sealer where required3-5 working days (estimate)Grout cured and sealing completed
Fit-offVanity, toilet, shower screen, tapware, lighting, fan4-6 working daysFixtures installed to spec
Testing and clean-downDrainage flow test, water connections, final clean1-2 working daysDrainage and every connection tested

Allow about five to eight weeks for on-site work on a mid-range Melbourne bathroom. Design, quoting and the permit pathway sit outside that window, typically three to seven weeks in total before anyone lifts a tile, and permit confirmation can overlap with late design work. Confirm the written permit pathway before strip-out, then keep the sign-off evidence for each stage before it is covered.

Where the dates actually move

Substrate repairs are a common source of delay because the condition of the floor and framing is often unclear until demolition exposes it. Soft particleboard, rotten nogging or a waste set too high can mean repairs and new floor falls before waterproofing starts. In the Brighton example, a two-day strip-out became a week of framing repairs and a new fall to the laundry waste.

Curing also governs the sequence. Follow the membrane product's data sheet, even if the tiler is available sooner. Before tiling, check that the substrate is sound and dry, the membrane work is documented, and the inspection evidence is recorded. A finished tile surface does not prove that waterproofing was installed or signed off correctly.

Build a two-week buffer into any promised finish date. Ask which hold point each stage must pass before the next begins, and do not let work be concealed before its inspection and records are complete.

What a Full Bath Remodel Costs in Melbourne

Place the job before you argue about tapware. A basic full bath remodel keeps the existing layout and waste. Mid-range allows a minor layout change and a tiled shower. Premium adds relocated plumbing, custom tiling, a wall-hung toilet and extras such as underfloor heating.

A price guide for a full bathroom remodel in Melbourne categorized into Basic, Mid-range, and Premium tiers.

TierTypical scopeWhere budgets usually grow
Basic refresh, same layoutLike-for-like layout, acrylic or tiled shower base, standard tapware and vanity, mid-grade tilesHidden subfloor rot and non-compliant waste
Mid-range remodelMinor layout change, tiled shower, floating vanity, heated towel rail, quality tiles, new lighting and exhaust fanMoving the waste or adding a window
Premium with layout changeRelocated plumbing, custom tiling, frameless screen, wall-hung toilet, underfloor heating, built-in storageStructural changes and long lead times on stone or custom joinery

Most Melbourne owners I would steer toward mid-range land there because that is where a cosmetic upgrade meets a proper wet-area build, not because it is the cheapest path. A basic refresh looks tidy until the old waste and the old membrane stay in place.

National approval figures won't tell you which band you're in. The Australian Bureau of Statistics Building Approvals methodology covers alterations and additions, approved non-structural renovation and refurbishment, and installation of integral fixtures, but it does not isolate bathrooms from kitchens, laundries and extensions.

How to read a quote

A fair quote splits the work so you can compare apples with apples:

  • Strip-out and disposal: tiles, vanity, linings and waste, not a single "demo" lump.
  • Rough-in: plumbing and electrical named separately, including the fan duct to outside.
  • Waterproofing and evidence: membrane system, photos and any certificate, not "included in tiling".
  • Tiles and setting materials: adhesive, grout and sealer called out, not buried in a square-metre rate.
  • Fixtures: supplied and fitted as their own lines, so a tap upgrade doesn't hide a labour change.
  • Screen, fan, paint and design fees: each on its own line.

Compare those lines, not the bottom total. A line-item full bathroom cost breakdown makes that comparison possible when the other quotes arrive as one number.

On older homes I would hold a contingency of 10 to 15 percent of the build cost. Say a Bentleigh bungalow is quoted at $24,000 for a mid-range job and the subfloor is soft once the vinyl comes up. Around $2,800 of extra sheeting and framing is a normal surprise, not a new project. The single test before you sign is this. Does this number include waterproofing and the evidence that it was done?

Layout and Accessible Design Choices That Last

A bathroom planned for use now and later costs little more than one that isn't, if you decide before the walls close. Waiting until someone needs a rail means opening tile you just paid to install.

Australian bathroom guidance referenced by My Homeware includes about 900 mm of clear space in front of a toilet and 450 mm on either side to the nearest obstruction. Check the door swing against that path. A door that opens into the toilet clearance looks fine on a plan and fails the first morning someone uses a walker, or carries a laundry basket.

A modern accessible bathroom featuring a walk-in glass shower, a vanity, a toilet, and grab bars.

Choices that belong in the layout, not a later retrofit

  • Level-entry shower: design the hob or step-down so the floor and that detail can be waterproofed, rather than adding a ramp over a finished tray.
  • Blocking for later rails: fix solid noggings or reinforced lining at likely grab positions before the sheets go on. Rails can wait. The backing cannot.
  • Lever handles: on taps and the door, so wet hands and weaker grip both work.
  • Slip-resistant floor: choose the finish for wet feet, not for a showroom photo.
  • Layered lighting: a switch at the door, plus task light at the mirror, so you aren't stepping into a dark wet room.
  • A seated position: a fold-down seat or a ledge sized for sitting, even if nobody needs it this year.

Small rooms still have room if you spend it carefully. A wall-hung vanity frees the floor for a mop and a wheelchair footplate. Recessed niches sit between studs instead of stealing shower width. A mirror cabinet replaces a separate shelf. A sliding or outward-opening door keeps the swing out of the circulation path. More ideas sit in this accessible bathroom design guide.

Duct the exhaust fan to outside, not into the roof space. Moisture dumped above the ceiling comes back as stained plaster and a musty robe.

An accessible bathroom is not automatically a safe one. Poor falls, glare, a slippery polish and a door parked in the walkway undo the clearances.

Mark the layout on the floor with painter's tape before you order the toilet, the screen or the vanity. If two people can't pass the tape, the drawing is wrong.

Fixtures and Finishes That Suit a Wet Area

Fixture choices have to be locked before rough-in, not after the tiler starts. A wall-hung toilet needs its in-wall frame before the lining goes on. A freestanding bath needs the floor structure checked for the filled weight. Tap centres are fixed once the wall is tiled, and moving them means cutting membrane.

ChoiceWorks best whenTrade-off to check
Large-format porcelain tile (600 x 600 mm or larger)Floor is flat and well prepared, and the room is wide enough to handle the tilesNeeds a flatter substrate and is harder to cut and handle in a small bathroom
Small-format mosaic tileShower floors need tight falls to the wasteMore grout lines to clean and seal
Matte porcelain floor tileWet-area floors where slip resistance mattersCheck the slip rating before selecting; polished finishes become hazardous underfoot
Honed natural stoneA premium look and consistent colour are requiredNeeds sealing on a schedule and costs more
Wall-hung toiletEasier cleaning and a lighter visual footprintNeeds an in-wall frame and a suitable wall; higher installation cost
Freestanding bathA feature piece in a larger roomTakes floor space, needs floor loading checked and a sealed perimeter
Floating vanitySmall bathrooms and easy floor cleaningNeeds solid backing fixed before lining; check lead time

The order that stops rework

Fix the layout first. Select and order the fixtures and tapware second. Select tiles third. Tile size has to suit the flatness you can really build. A 600 mm porcelain will lip if the sheet isn't true, and it's awkward to cut around a small-room waste. Mosaic follows a tight fall, then asks you to clean every joint. Grout width is a cleaning decision as much as a look. Wider joints hide movement and collect soap scum.

View sample boards in the bathroom, under the light you'll install, and wet them. Showroom halogen makes a warm grey look cold, and a matte tile can go glossy once it's damp. Polished floors are the finish I would refuse in a shower zone.

Custom screens, natural stone and some tapware take several weeks. Order them before the rough-in closes, or the fit-off week becomes a waiting week.

On a mid-range budget, spend on what you touch and see every day: tapware, the shower screen, lighting and the exhaust fan. Save on what sits behind tile, as long as the membrane system is specified properly. A cheap mixer that drips costs more than a mid-grade one that doesn't.

Before you pay a deposit, write down the toilet rough-in distance, tap centres, mirror and light positions, and vanity height. Those four numbers stop the "it doesn't fit" call.

Permits and Compliance Checks Before Demolition

A finished-looking bathroom proves nothing about the wet-area build. The defects that flood a ceiling sit behind the tiles, and a glossy grout line doesn't show them.

In Victoria the legal layers are plain enough once you separate them. The Victorian building standards guidance identifies the Building Act 1993, the Building Regulations 2018 and the Plumbing Regulations 2018 as the instruments that give legal effect to the National Construction Code. The Code sets design and construction requirements, including plumbing and drainage, and Victorian guidance points to wet-area waterproofing as part of that framework.

The mistake is treating the Code as if it automatically writes the rules for every alteration. The Australian Building Codes Board states that the NCC primarily applies to new building work, and that renovation requirements must also be determined under state and territory legislation. The useful question isn't "what is waterproofing?" It's which approvals, inspections, evidence and trades this exact change needs.

A professional contractor inspects bathroom floor joists with a moisture meter before a full bath remodel.

Sort the work before anyone swings a hammer

  1. List every change: fixtures, a moved waste, a removed wall, a new window, new lighting and the fan.
  2. Sort each item into cosmetic or regulated building or plumbing work.
  3. Ask the building surveyor or council to confirm the permit pathway in writing.
  4. Book a licensed plumber for regulated plumbing and keep the certificate.
  5. Schedule the inspection for before tiles conceal the membrane, and keep the record with the photos.

Older Melbourne houses change the list after demolition. Timber flooring beside the bath, earlier non-conforming waste work and concealed water damage can turn a fixture swap into regulated repairs. Photograph the substrate the day it's exposed.

If you rent the place out, keep approvals, certificates and photographs together for every regulated item. A visually complete bathroom is not the file a later buyer, insurer or tribunal will ask for.

How to Waterproof and Tile the Wet Area

The failure I see argued about most often starts with waterproofing treated as a paint job. Leaks begin at junctions, pipe penetrations, floor wastes, incompatible substrates and movement cracks, not in the middle of a flat wall.

An instructional infographic detailing the six-step process for properly waterproofing and tiling a bathroom wet area.

Under NCC Housing Provisions Part 10.2, a shower floor must be waterproof, shower walls must be waterproof to at least 1800 mm above the floor substrate, and wall junctions, wall-to-floor junctions and penetrations must be waterproof. The alternative Deemed-to-Satisfy pathway permits AS 3740:2021. Follow one defined pathway. Don't mix clauses from both.

The sequence, and where it usually slips

  1. Confirm the substrate is sound, flat and dry, and repair framing or sheeting first. A membrane over dust, voids or a damp sheet fails unnoticed, often months later.
  2. Set the finished floor level and the waste so the shower falls toward the outlet, commonly around 1:80, or as the membrane system and the design specify. A waste that sits proud forces a hump, and water sits in it.
  3. Prime, then apply a membrane compatible with that substrate, with bands or collars at corners, the wall-floor junction and every pipe. A brush coat that stops 10 mm short of a tap penetration is the usual miss.
  4. Waterproof the shower floor and the shower walls to at least 1800 mm above the floor substrate. Stopping at tile height because "the tile covers it" leaves the top of the wet zone bare.
  5. For an unenclosed shower, place a waterstop at least 1500 mm horizontally from the shower rose. That is why screen position is a design decision, not a fit-off decision.
  6. Photograph membrane coverage and every penetration before anything hides them. Keep product data sheets and the installer's record in the same folder.
  7. Allow the full cure time on the product data sheet. Tiling early because the tiler has a gap is how a soft membrane tears under the adhesive.
  8. Record the inspection before any tile is set. No photo, no record, no tile.
  9. Tile with a compatible adhesive, grout, and seal where that product requires it. A cement-based adhesive on a membrane that wants a specific system is a warranty void, not a shortcut.

The same logic applies beside a bath on a timber floor. The room floor in that zone has to be waterproofed, not just the splash area you can see. A practical walk-through of the site sequence is in this bathroom waterproofing procedure. If a stain is already showing in the ceiling below, get professional plumbing leak repairs to find the active leak before you bury a new membrane over a wet joist.

This short clip shows why the junctions, not the open wall, are the part worth watching.

Hire Trades and Lock In Milestones Before Work Starts

A plumber, electrician, waterproofer and tiler need to follow one shared sequence. Otherwise, a trade can cover work before the next inspection or sign-off. AS 3740:2021 is the Australian reference for domestic wet-area waterproofing materials, design and installation, and applies to relevant Class 1, Class 2 and Class 4 residential buildings. Ask for a record at each transition, including the hob or step-down, waterstop, floor waste, wall-floor junction, bath perimeter, tap penetrations and unenclosed splash zone. A bathroom that looks finished does not prove these details were checked.

Before hiring, check that each trade holds the licence required for its work, and confirm public liability and workers compensation cover. Get a written scope, a named trade for each stage and a written workmanship warranty. Agree on transparent pricing and guaranteed start and finish dates.

Put these hold points in the contract:

  1. Substrate repairs signed off before lining or membrane installation.
  2. Waterproofing inspection recorded, with membrane photos and product records attached.
  3. Plumbing and electrical rough-in sign-offs recorded.
  4. Tiling held until the waterproofing and rough-in records are complete.
  5. Drainage flow and every water connection tested before final payment.

These checks catch faults while they are still accessible. If tiling starts before an unresolved floor fall or missed collar is addressed, fixing it can mean removing tiles and disturbing the screen and waste.

Before signing, list the work required, photograph the existing room, including beneath the vanity and around the waste, and request the milestone schedule in writing. A free in-home consultation from Western Bathroom Renovations can help assess those items against the room.

Western Bathroom Renovations manages full bathroom renovations from layout and demolition through waterproofing, tiling and fit-off, with transparent pricing and guaranteed start and finish dates. If you are weighing a leaking shower against a full rebuild, book an in-home consultation and bring your quotes. Start at Western Bathroom Renovations.